Pwd Road Cutting Permission

Road cutting permission is required when a utility company or individual needs to dig up a portion of a public road for installing, repairing, or maintaining infrastructure like water pipes, electricity lines, or telecom cables.

pwd road cutting permission

Steps to Obtain Road Cutting Permission

  1. Application Submission:

    • Submit a formal application to the local PWD office. The application should include details like the purpose of cutting, location, dimensions of the area, and the timeline for the work.
  2. Documentation:

    • Attach necessary documents, such as:
      • Proof of ownership or authorization from the utility company.
      • Maps or diagrams indicating the location and extent of the cutting.
      • An environmental impact assessment (if required).
  3. Fee Payment:

    • Pay the applicable fee for processing the application. The fee varies based on the type of work and location.
  4. Site Inspection:

    • PWD officials may conduct a site inspection to assess the impact of the proposed cutting on road safety and traffic.
  5. Approval:

    • If everything is in order, the PWD will grant permission. This may include specific conditions to minimize disruption, such as traffic management plans.
  6. Execution:

    • Once permission is granted, the work can commence. The contractor must ensure the area is restored to its original condition after the work is completed.
  7. Completion Report:

    • After finishing the work, submit a completion report to the PWD, confirming that the road has been restored properly.

Important Considerations

  • Timing: Apply well in advance to avoid delays, especially if the work is urgent.
  • Compliance: Follow all safety and traffic regulations during the cutting process.
  • Restoration: Ensure proper restoration of the road to prevent accidents and further damage.

Procedure

Apply In-Person:

  1. Application for NOC for Road Cutting in Rajasthan is available in the Rajasthan Municipal Corporation contact link
  2. Applicant must provide all necessary information in the application form.
  3. Applicant should make sure to carry photocopies and originals of all documents that are needed for completing the procedure.
  4. Documents that are needed for completing the procedure are mentioned under “Required Documents” section of this page.
  5. Fees is calculated as – Utilized NH Land * Prevailing circle rate per square unit area/10*12 (Rs/sq ft/month).
  6. If all above-mentioned procedures were followed properly by the applicant, the application form will be accepted by concerned authorities.
  7. The application will be put up for any objection from public domains for 30 days.
  8. If there is no objection from any domain within 30 days, applicant will be called by concerned officials to collect their NOC certificate from the office.
  9. If there are no updates about application, applicant can reach the office to know status of their application.

Required Documents

  • Safety references from Directorate of Electricity, Chief Controller Explosives, Petroleum and Explosives safety Organization, Oil Industry Safety Directorate, State/Central Pollution Control Board.
  • Index/Key Plan
  • PAN number (Individual / Organization)
  • ID Proof
  • AADHAR Card (Individual)
  • Address Proof