Section 20 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Land to be marked out, measured and planned including marking of specific areas The Collector shall thereupon cause the land, unless it has been already marked out under section 12, to be marked out and measured, and if no plan has been made thereof, a plan to be made of the same. Practice area’s of […]

Section 20 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013 Read More »

Section 19 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Publication of declaration and summary of Rehabilitation and Resettlement (1) When the appropriate Government is satisfied, after considering the report, if any, made under sub-section (2) of section 15, that any particular land is needed for a public purpose, a declaration shall be made to that effect, along with a declaration of an area identified

Section 19 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013 Read More »

Section 18 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Approved Rehabilitation and Resettlement Scheme to be made public The Commissioner shall cause the approved Rehabilitation and Resettlement Scheme to be made available in the local language to the Panchayat, Municipality or Municipal Corporation, as the case may be, and the offices of the District Collector, the Sub-Divisional Magistrate and the Tehsil, and shall be

Section 18 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013 Read More »

Section 17 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Review of the Rehabilitation and Resettlement Scheme (1) The Collector shall review the draft Scheme submitted under sub-section (6) of section 16 by the Administrator with the Rehabilitation and Resettlement Committee at the Project level constituted under section 45. (2) The Collector shall submit the draft Rehabilitation and Resettlement Scheme with his suggestions to the

Section 17 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013 Read More »

Section 16 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Preparation of Rehabilitation and Resettlement scheme by the Administrator (1) Upon the publication of the preliminary notification under sub-section (1) of section 11 by the Collector, the Administrator for Rehabilitation and Resettlement shall conduct a survey and undertake a census of the affected families, in such manner and within such time as may be prescribed,

Section 16 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013 Read More »

Section 15 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Hearing of objections (1) Any person interested in any land which has been notified under sub-section (1) of section 11, as being required or likely to be required for a public purpose, may within sixty days from the date of the publication of the preliminary notification, object to— (a)   the area and suitability of

Section 15 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013 Read More »

Section 14 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Lapse of Social Impact Assessment report Where a preliminary notification under section 11 is not issued within twelve months from the date of appraisal of the Social Impact Assessment report submitted by the Expert Group under section 7, then, such report shall be deemed to have lapsed and a fresh Social Impact Assessment shall be

Section 14 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013 Read More »

Section 13 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Payment for damage The officer so authorised under section 12 shall at the time of entry under section 12 pay or tender payment for any damage caused, and, in case of dispute as to the sufficiency of the amount so paid or tendered, he shall at once refer the dispute to the decision of the

Section 13 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013 Read More »

Section 12 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Preliminary survey of land and power of officers to carry out survey For the purposes of enabling the appropriate Government to determine the extent of land to be acquired, it shall be lawful for any officer, either generally or specially authorised by such Government in this behalf, and for his servants and workmen,— (a)  

Section 12 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013 Read More »

Section 11 – Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation And Resettlement Act, 2013

Publication of preliminary notification and power of officers thereupon (1) Whenever, it appears to the appropriate Government that land in any area is required or likely to be required for any public purpose, a notification (hereinafter referred to as preliminary notification) to that effect along with details of the land to be acquired in rural