Road cutting permission is required when a utility company or individual needs to dig up a portion of a public road for installing, repairing, or maintaining infrastructure like water pipes, electricity lines, or telecom cables.
Steps to Obtain Road Cutting Permission
Application Submission:
- Submit a formal application to the local PWD office. The application should include details like the purpose of cutting, location, dimensions of the area, and the timeline for the work.
Documentation:
- Attach necessary documents, such as:
- Proof of ownership or authorization from the utility company.
- Maps or diagrams indicating the location and extent of the cutting.
- An environmental impact assessment (if required).
- Attach necessary documents, such as:
Fee Payment:
- Pay the applicable fee for processing the application. The fee varies based on the type of work and location.
Site Inspection:
- PWD officials may conduct a site inspection to assess the impact of the proposed cutting on road safety and traffic.
Approval:
- If everything is in order, the PWD will grant permission. This may include specific conditions to minimize disruption, such as traffic management plans.
Execution:
- Once permission is granted, the work can commence. The contractor must ensure the area is restored to its original condition after the work is completed.
Completion Report:
- After finishing the work, submit a completion report to the PWD, confirming that the road has been restored properly.
Important Considerations
- Timing: Apply well in advance to avoid delays, especially if the work is urgent.
- Compliance: Follow all safety and traffic regulations during the cutting process.
- Restoration: Ensure proper restoration of the road to prevent accidents and further damage.
Procedure
Apply In-Person:
- Application for NOC for Road Cutting in Rajasthan is available in the Rajasthan Municipal Corporation contact link
- Applicant must provide all necessary information in the application form.
- Applicant should make sure to carry photocopies and originals of all documents that are needed for completing the procedure.
- Documents that are needed for completing the procedure are mentioned under “Required Documents” section of this page.
- Fees is calculated as – Utilized NH Land * Prevailing circle rate per square unit area/10*12 (Rs/sq ft/month).
- If all above-mentioned procedures were followed properly by the applicant, the application form will be accepted by concerned authorities.
- The application will be put up for any objection from public domains for 30 days.
- If there is no objection from any domain within 30 days, applicant will be called by concerned officials to collect their NOC certificate from the office.
- If there are no updates about application, applicant can reach the office to know status of their application.
Required Documents
- Safety references from Directorate of Electricity, Chief Controller Explosives, Petroleum and Explosives safety Organization, Oil Industry Safety Directorate, State/Central Pollution Control Board.
- Index/Key Plan
- PAN number (Individual / Organization)
- ID Proof
- AADHAR Card (Individual)